IELO - Historique des incidents

Ile de France connaît une panne partielle

Remarque : Les incidents signalés sur cette interface ne concernent que les incidents génériques impactant les services de ielo.

Standard ielo - Opérationnel

Portail ielo - Opérationnel

Backbone - Opérationnel

Porte de collecte - Opérationnel

API - Opérationnel

Historique des incidents

01/12

Incident fibre Avignon (84)
  • Résolu
    Résolu

    Bonjour,

    L’intervention est terminée et l’ensemble des services est de nouveau actif.
    Cet incident est désormais clôturé.

    Cordialement,
    Support IELO


    Hello,

    The intervention is complete and all services are now back online.
    This incident is now closed.

    Regards,
    Support IELO

  • Surveillé
    Surveillé

    Bonjour,

    À ce jour, moins de 10 services restent en cours de réparation unitaire.
    Nous maintenons la chambre sous surveillance tant que l’intervention n’est pas terminée.

    Si vous rencontrez toujours une coupure, nous vous invitons à ouvrir un ticket d’incident le cas échéant.

    Une prochaine communication sera effectuée dès la fin de l’intervention.

    Cordialement,
    Support IELO



    Hello,

    As of now, fewer than 10 services are still undergoing individual repair.
    We are keeping the chamber under monitoring until the intervention is fully completed.

    If you are still experiencing an outage, please open an incident ticket if not already done.

    The next update will be provided once the intervention is completed.

    Regards,
    Support IELO

  • Mettre à jour
    Mettre à jour

    Bonjour,

    La plupart des liens impactés sont déjà remontés. Une équipe vient prendre la relève de l'équipe de nuit à 9h30 pour finaliser l'intervention et ressouder les dernières fibres.

    Prochaine communication à 11h.

    Cordialement,

    Support IELO


    Hello,

    Most of the damaged connections have already been repaired. A team will take over from the night shift at 9:30 a.m. to finalize the work and reconnect the last few fibers.

    Next update at 11 a.m.

    Regards,

    IELO Support

  • Mettre à jour
    Mettre à jour

    Nous poursuivons nos efforts pour rétablir le lien. Les soudures sont en cours et certains services sont déjà rétablis. Une nouvelle mise à jour sera communiquée d’ici 2 heures.


    We are continuing our efforts to restore the link. Splicing is in progress and some services have already been restored. A further update will be provided within the next 2 hours.

  • Identifié
    Identifié

    Le tirage des câbles est toujours en cours. Une mise à jour vous sera transmise dès la fin de l’opération.

    __________________________________

    Cable pulling is still in progress. An update will be provided as soon as the operation is complete.

  • Surveillé
    Surveillé

    Bonjour,

    Nos équipes sont arrivées sur place.

    Celles-ci balisent la zone.

    L'opération de tirage devrait bientôt commencer.

    Cordialement,

    Support IELO

    ______________________________________________

    Hello,

    Our teams have arrived on site.

    They are marking out the area.

    The pulling operation should begin shortly.

    Kind regards,

  • Identifié
    Identifié

    Bonjour,

    Un câble sectionné a été identifié.

    Une intervention de tirage est nécessaire.

    Nous avons mobilisé des ressources humaines supplémentaires.

    L'opération de tirage devrait commencer entre 20h00 et 20H30.

    Une communication sur le début de tirage vous sera faites dès que celle-ci commencera.

    Cordialement,

    Support IELO


    ________________________________________________________

    Hello,

    A severed cable has been identified.

    A pulling operation is required.

    We have mobilised additional human resources.

    The pulling operation should begin between 8:00 p.m. and 8:30 p.m.

    You will be notified as soon as the pulling operation begins.

    Kind regards,

    IELO Support

  • Mettre à jour
    Mettre à jour

    Bonjour,

    Notre technicien est actuellement sur la zone de la coupure et les investigations sont en cours.

    Une prochaine communication sera effectuée à 18h00 (heure locale).

    Cordialement,

    Support IELO

    ---

    Hello,

    Our technician is currently on the outage area and investigations are ongoing.

    The next update will be provided at 17:00 UTC.

    Regards,

    Support IELO

  • Détecté
    Détecté

    Bonjour,

    Un incident générique impacte actuellement plusieurs de nos services à Avignon (84).

    Des travaux ont été signalés sur zone.

    Une équipe d’intervention a été déclenchée et des investigations sont en cours afin d’en déterminer l’origine.

    Une prochaine communication sera effectuée à 17h30 (heure locale).

    Cordialement,

    Support IELO

    ---

    Hello,

    A generic incident is currently impacting several of our services in Avignon (84).

    Construction work has been reported in the area.

    A field team has been dispatched, and investigations are underway to determine the root cause.

    The next update will be provided at 16:30 UTC.

    Regards,

    Support IELO

01/11

Coupure sur notre réseau WDM entre Montpellier et Nimes
  • Résolu
    Résolu

    Les services sont stables, nous clôturons cet incident.

    ---

    Services are stable. We are closing this incident.

  • Surveillé
    Surveillé

    Les fibres ont été swappées. La liaison est de nouveau opérationnelle. Nous gardons en observation quelques heures.

    ---

    Fibers have been swapped. Link is operational. We keep monitoring the stability for a couple of hours.

  • Identifié
    Identifié

    Le point de coupure est identifié. Notre équipe va procéder à un swap de fibres.

    ---

    Fiber cut point is identified. Our team is going to proceed to a fiber swap.

  • Mettre à jour
    Mettre à jour

    Notre équipe est sur zone, et affine la localisation du point d'impact.

    ---

    Our team is currently on site, and is narrowing the location of the impact point.

  • Mettre à jour
    Mettre à jour

    Notre équipe sera sur place à 1h30 environ (UTC+1).

    ---

    Our team will be on site at appr. 1h30AM (UTC+1).

  • Détecté
    Détecté

    Bonsoir,

    Nous subissons actuellement une coupure sur notre réseau WDM entre Montpellier et Nimes. La coupure a été prélocalisée par réflectométrie près de notre POP de Montpellier. Nous déclenchons nos équipes d'intervention.

    ---

    Hello,

    We are currently facing a fiber cut on our WDM network between Montpellier and Nimes. Fiber cut has beenb prelocated with OTDR shot near our POP in Montpellier. We are sending a team on site.

Incident bakbone Pont-l'Évêque (14)
  • Résolu
    Résolu
    This incident has been resolved.
  • Surveillé
    Surveillé

    Bonjour,

    Nos équipes sont arrivées sur le lieu de la défaillance et ont constatées que notre câble est endommagé, nos techniciens ont effectués les réparations nécessaires et l'intervention est terminée.

    Nous confirmons que l'ensemble des circuits WDM transitants par ces câbles sont de nouveau opérationnels.

    Nous conservons néanmoins ce câble sous monitoring quelques heures.

    Cordialement,

    ---

    Hello,

    Our teams have completed the repair work. We observed damage to a Long-Haul IELO cable.

    Our teams have carried out the necessary repairs.

    All connections are currently back up and running.

    We are keeping the connection under monitoring.

    Regards

  • Identifié
    Identifié

    Notre équipe est arrivée sur la zone d'impact, les investigations sont en cours,

    ---

    Our team has arrived at the impact site, investigations are underway,

  • Mettre à jour
    Mettre à jour

    Notre équipe est encore en route, décision a été prise de leur demander de passer récupérer du câble en préventif, ce qui les a retardés.

    ---

    Our team is still on its way to the site. Decision was made to preventively ask them to go pick some cable, thus delaying their arrival.

  • Mettre à jour
    Mettre à jour

    Bonjour,

    L’équipe terrain est en route vers la zone impactée, avec une ETA prévue à 19h00 (heure locale).

    La prochaine communication sera effectuée à 19h00 ou dès que nous aurons des informations supplémentaires.

    Cordialement,

    Support IELO

    ---

    Hello,

    The field team is currently on its way to the impacted area, with an ETA scheduled for 18:00 UTC.

    The next update will be provided at 18:00 UTC or as soon as additional information becomes available.

    Regards,

    Support IELO

  • Détecté
    Détecté

    Bonjour,

    Nous détectons une coupure sur l'une de nos interconnexions core WDM sur le secteur de Pont L’évèque.

    Des investigations sont en cours pour connaitre l'origine.

    Une équipe a été déclenchée.

    Prochaine communication : 15h45

    Cordialement

    Support Ielo

    ---

    Hello,

    We are currently observing a cutoff on one of our interconnections near Pont L’évèque.

    Investigations are underway to determine the root cause.

    A field team has been dispatched to the site.

    The next update will be provided at 14:45 UTC.

    Regards,

    Support IELO

Incident Bourg-Saint-Maurice (73)
  • Résolu
    Résolu

    Bonjour,

    La cause de cette coupure était liée à une maintenance électrique réalisée par le gestionnaire du site.

    Cette maintenance est désormais terminée et l’incident est clos.

    Si vous rencontrez toujours une coupure, veuillez nous l’indiquer via un ticket d’incident.

    Cordialement,

    Support IELO

    ---

    Hello,

    The root cause of this outage was an electrical maintenance operation carried out by the site manager.

    This maintenance is now completed, and the incident is closed.

    If you are still experiencing a service interruption, please report it via an incident ticket.

    Regards,

    Support IELO

  • Surveillé
    Surveillé

    Nos services sont de nouveau actifs. Nous avons demandé un compte rendu détaillé à nos équipes sur place.

    L’incident reste sous monitoring ; si vous constatez toujours une coupure de service, nous vous invitons à nous en informer via votre ticket d’incident.

    Notre prochaine communication est prévue à 11h45 (heure locale).

    Cordialement,

    Support IELO

    ---

    Our services are back online. A detailed report has been requested from our on-site teams.

    The incident remains under monitoring; if you are still experiencing a service interruption, please inform us through your incident ticket.

    Our next update is scheduled for 10:45 UTC.

    Regards,

    Support IELO

  • Identifié
    Identifié

    Bonjour,

    Notre équipe est désormais sur place et a débuté les investigations.

    Nous reviendrons vers vous dès que nous aurons davantage d’informations.

    Notre prochain point de communication est prévu à 11h15 (heure locale).

    Cordialement,

    Service d’Exploitation IELO

    ---

    Hello,

    Our team is now on site and has started the investigations.

    We will update you as soon as additional information becomes available.

    Our next communication is scheduled for 10:15 UTC.

    Regards,

    IELO Operations Service

  • Détecté
    Détecté

    Bonjour,

    Nous subissons actuellement une interruption de services à Bourg-Saint-Maurice.

    Nos équipes sont mobilisées et investiguent afin de déterminer la cause racine de l’incident. Une interruption électrique sur zone est actuellement suspectée.

    Un technicien, déjà à proximité, est en route vers le site pour effectuer les premières vérifications.

    Une prochaine mise à jour sera communiquée lors de notre point de synchronisation prévu à 10h30 (heure locale).

    Cordialement,

    Service d’Exploitation IELO


    Hello,

    We are currently experiencing a service outage in Bourg-Saint-Maurice.

    Our teams are actively investigating to determine the root cause, with a suspected power interruption in the area.

    A technician who is already nearby is heading to the site to perform the initial checks.

    The next update will be provided during our scheduled synchronization point at 09:30 UTC.

    Regards,

    IELO Operations Service

Incident fibre Neuilly sur Seine (92)
  • Résolu
    Résolu

    Bonjour,

    L'opération de raccordement est terminée.

    L'intégralité des services est rétablie.

    N'hésitez pas à nous remonter tout défaut via vos tickets de support.

    Merci,

    Cordialement,

    __________________________

    Hello,

    The connection operation has been completed.

    All services have been restored.

    Please don't hesitate to report any issues through your support tickets.

    Thank you,

    Best regards

  • Mettre à jour
    Mettre à jour

    Bonjour,

    Les travaux sur cet incident sont toujours en cours.

    Nos équipes fibres sont actuellement pleinement mobilisées sur les raccordements.

    Vos services seront rétablis progressivement au fur et à mesure des raccordements.

    Cordialement,

    Support IELO.

    _____________________________

    Hello,

    Work on this incident is still ongoing.

    Our fibre teams are currently fully focused on reconnections.

    Your services will be gradually restored as connections are made.

    Kind regards,

    IELO

  • Mettre à jour
    Mettre à jour

    Bonsoir,

    Les raccordements sont toujours en cours. Nous avons mobilisé tous les moyens nécessaires afin de rétablir les liens dans les meilleurs délais.

    Nous vous remercions de votre patience.

    Cordialement,


    Good evening,

    The connections are still in progress. We have mobilized all necessary resources to restore the links as soon as possible.

    Thank you for your patience.

    Kind regards,

  • Mettre à jour
    Mettre à jour

    Mise à jour – Incident en cours

    Le tirage des câbles est désormais terminé.

    Nos équipes vont à présent commencer les opérations de raccordement.

    Nous vous tiendrons informés de l’avancement des travaux.


    Cordialement,

    ___

    English version

    Subject: Update – Ongoing Incident

    Cable pulling has been completed.

    Our teams are now starting the reconnection operations.


    We will keep you informed of the progress.


    Kind regards,

  • Mettre à jour
    Mettre à jour

    Bonjour,

    Le tirage se poursuit, avec une fin estimée à 18h30 (heure locale).
    Vos services seront rétablis progressivement au fur et à mesure des raccordements post-tirage.
    Nous avons relancé nos équipes afin d’obtenir l’ETR définitive de l’intervention.

    Prochaine communication à 18h30 (heure locale) ou dès que de nouvelles informations seront disponibles.

    Cordialement,
    Support IELO



    Hello,

    Cable pulling is still ongoing, with completion estimated at 17:30 UTC.
    Your services will be gradually restored as post-pulling connections are completed.
    We have followed up with our field teams to obtain a definitive ETR for the intervention.

    Next update scheduled for 17:30 UTC or sooner if new information becomes available.

    Regards,
    Support IELO

  • Mettre à jour
    Mettre à jour

    Bonjour,

    L’intervention se poursuit, le tirage du câble est toujours en cours.
    Nous n’avons pas encore d’estimation de rétablissement (ETR) à ce stade, une relance a été effectuée auprès de nos équipes terrain.

    Notre prochain point de synchronisation est prévu à 15h30 (heure locale).

    Cordialement,
    Support IELO


    Hello,

    The intervention is still ongoing, and cable pulling is in progress.
    We do not yet have an estimated time of restoration (ETR); our field teams have been reminded accordingly.

    The next update is scheduled for 14:30 UTC.

    Regards,
    Support IELO

  • Identifié
    Identifié

    Bonjour,

    Nous avons identifié la cause de la coupure.


    Des câbles ont été endommagés suite à l’intervention d’un tiers non identifié.

    Nos équipes procèdent actuellement au tirage d’un nouveau câble sur une distance estimée entre 460 et 700 mètres.
    Compte tenu de l’ampleur des travaux, nous ne disposons pas encore d’une estimation de rétablissement (ETR).

    Toutes nos équipes restent pleinement mobilisées afin de rétablir vos services dans les meilleurs délais.

    Prochaine communication à 13h00 (heure locale) ou dès que de nouvelles informations seront disponibles.

    Cordialement,
    Support IELO



    Hello,

    We have identified the cause of the outage.


    Cables were damaged following the intervention of an unidentified third party.

    Our teams are currently pulling a new cable over an estimated distance of 460

    to 700 meters.
    Given the scope of the work, we do not yet have an estimated time of restoration (ETR).

    All our teams remain fully mobilized to restore your services as quickly as possible.

    Next update at 12:00 UTC or as soon as additional information becomes available.

    Regards,
    Support IELO

    Câbles impactés .jpeg
  • Mettre à jour
    Mettre à jour

    Bonjour,

    Notre équipe est à présent sur place.
    Les investigations sont en cours afin d’identifier la cause de l’incident.

    La prochaine communication est prévue à 12h00 (heure locale).

    Cordialement,
    Support IELO


    Hello,

    Our team is now on site.
    Investigations are ongoing to identify the root cause of the incident.

    The next update is scheduled for 11:00 UTC.

    Regards,
    Support IELO

  • Mettre à jour
    Mettre à jour

    Bonjour,


    L’équipe d’intervention est en route, avec une ETA prévue à 11h20 (heure locale).

    Une prochaine communication sera effectuée à 11h30 (heure locale) ou dès que nous aurons des informations supplémentaires.

    Cordialement,
    Support IELO


    Hello,


    The field team is on its way, with an ETA scheduled for 10:20 UTC.

    The next update will be provided at 11:30 UTC or as soon as additional information becomes available.

    Regards,
    Support IELO

  • Détecté
    Détecté

    Bonjour,

    Un incident générique impacte actuellement plusieurs de nos services à Neuilly-sur-Seine (92).

    Une équipe d’intervention a été déclenchée et des investigations sont en cours afin d’en déterminer l’origine.

    Une prochaine communication sera effectuée à 10h35 (heure locale).

    Cordialement,

    Support IELO

    ---

    Hello,

    A generic incident is currently impacting several of our services in Neuilly-sur-Seine (92).

    A field team has been dispatched, and investigations are ongoing to determine the root cause.

    The next update is scheduled at 09:35 UTC.

    Regards,

    Support IELO

01/10

Incident acces sur le secteur de LOGNES (77) Magny-le-Hongre (77) Tremblay-en-France (93) Sarcelles (95)
  • Postmortem
    Postmortem

    Ruptures de fibre optique multiples et successives impactant plusieurs POPs en Île-de-France.

    Informations d’identification de l’incident

    Élément

    Détail

    Date et heure de début de l’incident

    11:47 31/10/2025 UTC+1

    Date et heure de fin de l’incident

    23:03 31/10/2025 UTC+1

    Durée totale de l’incident

    11 heures et 16 minutes

    Numéro de référence de l’incident

    #301583

    Date de rédaction du rapport

    03-11-2025

    Version du rapport

    1.4

    23:03

    31/10/2025

    Nature de l’incident

    Incident majeur de type rupture de fibre optique, résultant de deux événements de dégradation physiques, distincts et quasi-simultanés sur notre infrastructure réseau.

    ### Impact pour le client final

    Cet incident a provoqué une indisponibilité totale des services d'accès réseau pour les clients raccordés sur les points de présence (POP) suivants :

    • Créteil

    • Magny-le-Hongre

    • Tremblay-en-France

    • Sarcelles

    Les services impactés incluaient des liaisons FTTO, Lan-to-Lan, ainsi que le trafic Backbone et les interconnexions régionales, pour une durée totale de 11 heures et 16 minutes.

    Contexte et conditions

    Le 31 octobre 2025, nos systèmes de supervision ont détecté de multiples pertes de signal sur notre réseau métropolitain en Île-de-France. Les diagnostics initiaux ont rapidement révélé que ces alertes provenaient de deux coupures physiques distinctes mais géographiquement proches (Lognes et Magny-le-Hongre), dont la concomitance a entraîné l'isolement complet de plusieurs POP en cascade.

    Cause racine

    L'analyse approfondie menée par nos équipes techniques a identifié deux causes racines distinctes, dont la combinaison est à l'origine de l'indisponibilité :

    1. Coupure A (Lognes) : Action d'un tiers. Une entreprise externe, intervenant dans une chambre de télécommunication, a endommagé une de nos boîtes d'épissurage, provoquant une première rupture optique franche.

    2. Coupure B (Magny-le-Hongre) : Dégradation d'infrastructure. Une forte contrainte mécanique sur des fourreaux en entrée d'une seconde boîte d'épissurage a entraîné leur pliure et leur rupture, causant une seconde coupure optique.

    L'occurrence simultanée de ces deux pannes sur des segments différents du réseau a neutralisé les chemins de redondance et a provoqué l'isolement des POPs mentionnés ci-dessus.

    Action corrective et résolution

    Pour garantir un rétablissement des services dans les meilleurs délais, les actions suivantes ont été menées :

    1. Mobilisation immédiate : Deux équipes techniques spécialisées ont été dépêchées simultanément sur les deux points de coupure identifiés.

    2. Réparation de la Coupure A (Lognes) : Prise de contact avec l'entreprise tierce présente sur site et réparation de la boîte d'épissurage endommagée.

    3. Réparation de la Coupure B (Magny-le-Hongre) : Intervention sur la boîte d'épissurage et reprise des fourreaux dégradés pour supprimer les contraintes physiques.

    4. Rétablissement partiel : En parallèle, notre centre d'exploitation a mis en œuvre une solution de contournement réseau pour restaurer une partie des services de manière anticipée.

    5. Rétablissement complet et supervision : Une fois les réparations physiques terminées, l'ensemble du trafic a été validé. Une surveillance renforcée a été mise en place pour s'assurer de la stabilité des services.

    Responsabilité de l’incident

    La responsabilité de cet incident est attribuée à des tiers externes :

    • Une entreprise tierce identifiée, responsable des dommages à Lognes.

    • Une dégradation de l'infrastructure à Magny-le-Hongre, vraisemblablement due à une intervention tierce antérieure non identifiée.

    Synthèse chronologique des événements

    Heure (UTC+1)

    Date

    Événement

    11:47

    31/10/2025

    Détection : Multiples alarmes de perte de signal sur le réseau. Lancement du diagnostic.

    12:15

    31/10/2025

    Prise en charge : Déclenchement d'une première équipe terrain vers Lognes (Coupure A).

    12:35

    31/10/2025

    Investigation : Détection d'une seconde coupure à Magny-le-Hongre (Coupure B). L'impact s'étend et isole les POPs de Créteil, Magny-le-Hongre, Tremblay et Sarcelles.

    12:42

    31/10/2025

    Intervention : Déclenchement d'une seconde équipe terrain vers Magny-le-Hongre.

    13:12

    31/10/2025

    Arrivée de l'équipe 1 à Lognes. Confirmation de la cause (boîte endommagée par un tiers). Début des réparations.

    14:26

    31/10/2025

    Arrivée de l'équipe 2 à Magny-le-Hongre. Confirmation de la cause (fourreaux pliés). Début des réparations.

    15:50

    31/10/2025

    Résolution partielle : Mise en place d'une solution de contournement par l'exploitation. Rétablissement des premiers services.

    18:41

    31/10/2025

    Reprise progressive confirmée sur plusieurs services Backbone.

    23:03

    31/10/2025

    Résolution : Rétablissement complet de tous les services. Mise en place d'une surveillance renforcée.

    Conclusion

    L'incident du 31 octobre 2025 a été causé par une coïncidence exceptionnelle de deux ruptures de fibre distinctes, imputables à des interventions ou dégradations tierces. La mobilisation coordonnée de nos équipes d'exploitation et de nos techniciens terrain a permis de mettre en place une solution de contournement pour limiter la durée d'indisponibilité, avant un rétablissement complet des services à 23:03.

    ----

    International version

    Multiple and successive fiber optic cuts impacting several Points of Presence in the Île-de-France region.

    Incident Identification Details

    Item

    Detail

    Incident Start Date and Time

    11:47 31/10/2025 UTC+1

    Incident End Date and Time

    23:03 31/10/2025 UTC+1

    Total Incident Duration

    11 hours and 16 minutes

    Incident Reference Number

    #301583

    Report Creation Date

    03-11-2025

    Version du rapport

    1.4

    Nature of the Incident

    Major incident classified as a fiber optic cut, resulting from two distinct and nearly simultaneous physical degradation events on our network infrastructure.

    Impact for the End Customer

    This incident caused a complete outage of network access services for customers connected to the following Points of Presence (POP):

    • Créteil

    • Magny-le-Hongre

    • Tremblay-en-France

    • Sarcelles

    The impacted services included FTTO links, Lan-to-Lan services, as well as Backbone traffic and regional interconnections, for a total duration of 11 hours and 16 minutes.

    Context and Conditions

    On October 31, 2025, our monitoring systems detected multiple signal loss alarms on our metropolitan network in the Île-de-France region. Initial diagnostics quickly revealed that these alerts originated from two distinct but geographically close physical cuts (Lognes and Magny-le-Hongre), the combination of which led to the complete isolation of several POPs in a cascading effect.

    Root Cause

    The in-depth analysis conducted by our technical teams identified two distinct root causes, the combination of which led to the outage:

    1. Cut A (Lognes): Third-party action. An external company, working in a telecommunications manhole, damaged one of our splice closures, causing an initial, clean fiber optic break.

    2. Cut B (Magny-le-Hongre): Infrastructure degradation. Severe mechanical stress on ducts at the entry point of a second splice closure caused them to bend and break, resulting in a second fiber optic cut.

    The simultaneous occurrence of these two failures on different network segments neutralized redundancy paths and caused the isolation of the aforementioned POPs.

    Corrective Action and Resolution

    To ensure service restoration as quickly as possible, the following actions were taken:

    1. Immediate Mobilization: Two specialized technical teams were dispatched simultaneously to the two identified cut locations.

    2. Repair of Cut A (Lognes): Contact was made with the third-party company on-site, and the damaged splice closure was repaired.

    3. Repair of Cut B (Magny-le-Hongre): Work was performed on the splice closure and the damaged ducts were repaired to remove the physical stress.

    4. Partial Restoration: In parallel, our Network Operations Center implemented a network workaround to restore a portion of the services ahead of schedule.

    5. Full Restoration and Monitoring: Once the physical repairs were completed, all traffic was validated. Enhanced monitoring was put in place to ensure the stability of the services.

    Incident Responsibility

    Responsibility for this incident is attributed to external third parties:

    • An identified third-party company, responsible for the damage in Lognes.

    • Infrastructure degradation in Magny-le-Hongre, likely due to a previous, unidentified third-party intervention.

    Chronological Summary of Events

    Time (UTC+1)

    Date

    Event

    11:47 AM

    31/10/2025

    Detection: Multiple signal loss alarms on the network. Diagnostics initiated.

    12:15 PM

    31/10/2025

    Acknowledgment: First field team dispatched to Lognes (Cut A)

    12:35 PM

    31/10/2025

    Investigation: A second cut is detected in Magny-le-Hongre (Cut B). The impact expands, isolating the POPs of Créteil, Magny-le-Hongre, Tremblay, and Sarcelles.

    12:42 PM

    31/10/2025

    Intervention: A second field team is dispatched to Magny-le-Hongre.

    13:12 PM

    31/10/2025

    Team 1 arrives in Lognes. Cause confirmed (splice closure damaged by a third party). Repairs begin.

    14:26 PM

    31/10/2025

    Team 2 arrives in Magny-le-Hongre. Cause confirmed (bent ducts). Repairs begin.

    15:50 PM

    31/10/2025

    Partial Resolution: A workaround is implemented by the operations team. Initial services are restored.

    18:41 PM

    31/10/2025

    Progressive recovery confirmed on several Backbone services.

    23:03 PM

    31/10/2025

    Resolution: Full restoration of all services. Enhanced monitoring is in place. |

    Conclusion

    The incident on October 31, 2025, was caused by an exceptional coincidence of two separate fiber cuts, attributable to third-party interventions or degradation. The coordinated mobilization of our operations and field technician teams allowed for the implementation of a workaround to limit the duration of the outage, before a full restoration of services at 11:03 PM.

  • Résolu
    Résolu

    Bonjour,

    L'incident est terminé depuis le 31/10/2025 23H30, les services sont stables,

    Nous clôturons l'incident,

    Un RFO sera fourni via les tickets d'incident sur le portail IELO prochainement,


    -------------------------

    The incident ended on October 31, 2025, at 11:30 p.m. Services are stable.

    We are closing the incident.

    An RFO will be provided via incident tickets on the IELO portal shortly.

  • Surveillé
    Surveillé


    Chers clients,
    L’incident ayant affecté certains de nos services est désormais résolu.


    Nos équipes d’intervention ont terminé leurs actions correctives, et l’ensemble des services impactés est pleinement rétabli.


    Nous restons attentifs à toute éventuelle anomalie : n’hésitez pas à nous en faire part via vos tickets d’incident.


    Les liens concernés font toujours l’objet d’une surveillance renforcée afin de garantir la stabilité du service.
    Nous vous remercions sincèrement pour votre compréhension et votre patience.


    Cordialement,

    __

    Dear Customers,

    The incident that affected some of our services has now been fully resolved.

    Our intervention teams have completed the corrective actions, and all impacted services are now fully operational.

    We remain attentive to any potential issues — please don’t hesitate to report them through your incident tickets.

    The affected links are still under enhanced monitoring to ensure continued stability.

    We sincerely thank you for your understanding and patience.

    Kind regards,

  • Mettre à jour
    Mettre à jour

    Chers clients,

    Nos équipes d’intervention finalisent actuellement leurs actions sur la partie impactée par l’incident.
    Une reprise progressive des services backbone est en cours.

    Nous vous invitons à nous signaler toute remontée de vos services via les tickets d’incident correspondants.
    Nos équipes restent pleinement mobilisées afin de rétablir l’ensemble des services impactés dans les meilleurs délais, avec une priorité donnée aux plus critiques.

    Nous vous remercions de votre compréhension et de votre patience.

    Cordialement,

    __

    Dear Customers,

    Our intervention teams are currently finalizing their work on the affected components.
    Backbone services are gradually being restored.

    We kindly ask you to report any service recovery through your existing incident tickets.
    Our teams remain fully mobilized to restore all impacted services as quickly as possible, giving priority to the most critical ones.

    Thank you for your understanding and patience.

    Best regards,

  • Mettre à jour
    Mettre à jour

    Nos équipes d'exploitation ont finalisé le déploiement d'une solution de contournement pour rétablir les services actifs sur plusieurs de nos POP. La liste exhaustive des POP concernés est en cours de consolidation et vous sera communiquée dès que possible.

    Actuellement, les équipes de support effectuent des vérifications approfondies pour valider le bon fonctionnement et la stabilité des services rétablis.

    En parallèle, nous avons identifié la cause racine de l'interruption de service. L'incident provient d'une forte dégradation de notre infrastructure physique : une boîte d'épissurage dans une chambre de télécommunication a été endommagée par un tiers.

    Nos équipes sur le terrain priorisent désormais la réparation des fibres critiques, notamment celles assurant la connectivité des POP et les fibres noires exploitées par nos clients.

    Nous vous tiendrons informés de l'avancement des réparations.


    Our operations teams have successfully deployed a workaround to restore active services on several of our PoPs. A comprehensive list of the affected PoPs is being compiled and will be shared shortly.

    Currently, our support teams are conducting thorough checks to validate the functionality and stability of the restored services.

    In parallel, we have identified the root cause of the service disruption. The incident was traced back to significant physical infrastructure damage: a splice closure in a telecom manhole was severely damaged by a third party.

    Our field teams are now prioritizing the repair of critical fibers, specifically those connecting the PoPs and the dark fiber links used by our customers.

    We will keep you updated on the progress of the repairs.

    Image boite d'epissurage

  • Mettre à jour
    Mettre à jour

    Bonjour,

    Notre seconde équipe terrain arrive sur le site d'appui d'ici 15 minutes.

    Les analyses sont toujours en cours .

    Nous ferons une mise à jour de la situation d'ici une heure.

    Cordialement,

    L'équipe Support IELO


    Hello,

    Our second field team will arrive at the support site within 15 minutes.

    Analyses are still ongoing.

    We will provide an update on the situation within an hour.

    Best regards,

    The IELO Support Team

  • Identifié
    Identifié

    Nouveaux éléments sur l’incident :

    Les boîtes d’épissurage dans la chambre télécom de Lognes ont effectivement été endommagées par les techniciens tiers, mais nous restons prudents quant à l’exclusivité de cette cause racine. Les observations actuelles suggèrent un scénario multifacteur possible

    Actions en cours :

    • Analyse de l’infrastructure fibre :

    • Vérification systématique de l’intégrité de tous les câbles

    Préparation des réparations :

    • Priorisation des liens critiques (ex. : POP Créteil, Magny-le-Hongre) pour un rétablissement phasé.

    Investigation complémentaire :

    • Une seconde équipe est déployée vers le site d’appui (backhaul) pour vérifier :

    • L’état des connexions amont/aval.

    • La présence éventuelle de défauts sur les chambres intermédiaires.

    New information about the incident:

    The splice boxes in the Lognes telecoms room were indeed damaged by third-party technicians, but we remain cautious about this being the sole root cause. Current observations suggest a possible multi-factor scenario.

    Actions in progress:

    • Analysis of the fibre infrastructure:

    • Systematic verification of the integrity of all cables.

    Preparation of repairs:

    • Prioritisation of critical links (e.g. POP Créteil, Magny-le-Hongre) for a phased restoration.

    Additional investigation:

    • A second team is deployed to the backhaul site to check:

    • The status of upstream/downstream connections.

    • The possible presence of faults in the intermediate chambers

  • Mettre à jour
    Mettre à jour

    Bonjour,

    Nouveau point sur l’incident : Nos équipes sont maintenant sur place au POP de Lognes et collaborent avec une équipe tierce présente dans la chambre télécom alimentant notre infrastructure. Les actions en cours :

    • Échange technique avec les intervenants pour :

      • Identifier les travaux récents effectués sur nos liens/équipements.

      • Vérifier d’éventuelles interventions non planifiées (ex. : maintenance, réparation fibre).

    • Inspection visuelle des câbles et connecteurs pour détecter des anomalies physiques.

    Prochaine communication :

    • Sous 30 minutes (ou dès confirmation d’une cause ou d’un plan d’action).

    • Focus : Validation de l’origine du problème (tierce ou interne) et steps correctifs.

    Nous restons mobilisés pour un rétablissement rapide. Merci de votre patience.

    Cordialement,



    Latest incident update: Our teams are now on-site at the Lognes POP and coordinating with a third-party technician team working in the telecom room supplying our infrastructure. Current actions:

    • Technical debrief with the on-site crew to:

      • Confirm any recent work performed on our links/equipment.

      • Check for unplanned interventions (e.g., fiber maintenance/repair).

    • Physical inspection of cables/connectors for visible faults.

    Next communication:

    • Within 30 minutes (or sooner if root cause/action plan is confirmed).

    • Focus: Determining whether the issue originates from third-party or internal factors, and corrective steps.

    We are fully engaged to resolve this promptly. Thank you for your patience.

  • Mettre à jour
    Mettre à jour

    Bonjour à toutes et tous,

    Les perturbations initialement localisées à Lognes se sont étendues, avec des dégradations majeures à indisponibilités totales sur les POP suivants :

    Créteil

    Magny-le-Hongre

    Tremblay-en-France

    Sarcelles

    Actions en cours :

    Diagnostic approfondi pour identifier la cause racine (hypothèse prioritaire : rupture de fibre optique près de Lognes affectant les interconnexions), nos équipes terrains sont en route.

    Plan de contournement actif :

    Prochaines étapes :

    Mise à jour sous 1h (ou dès confirmation d'une solution de contournement).

    Nous comprenons l’urgence de la situation et mettons tout en œuvre pour rétablir les services

    The disruptions initially localised in Lognes have spread, with major damage and total unavailability on the following POPs:

    Créteil

    Magny-le-Hongre

    Tremblay-en-France

    Sarcelles

    Actions in progress:

    In-depth diagnosis to identify the root cause (priority hypothesis: fibre optic break near Lognes affecting interconnections), our field teams are on their way.

    Active workaround plan:

    Next steps:

    Update within 1 hour (or as soon as a workaround solution is confirmed).

    We understand the urgency of the situation and are doing everything possible to restore services.


  • Détecté
    Détecté

    Bonjour à tous,

    Nous confirmons une perturbation majeure sur le secteur de Lognes depuis 11:47, suivie d’une indisponibilité totale du POP local depuis 12:38. Nos équipes techniques sont déjà mobilisées pour diagnostiquer la cause.

    Premières observations :

    • Aucun défaut matériel ou électrique identifié à ce stade.

    • Investigations en cours pour isoler l’origine (lien optique, équipement tiers, etc.).

    Nous vous tiendrons informés dès que possible avec une estimation de rétablissement et des détails techniques complémentaires. Merci de votre patience.

    Prochaine mise à jour : sous 30 minutes (ou dès avancée significative).

    Cordialement,

    ---

    Hello

    We are experiencing a major disruption in the Lognes area since 10:47 UTC, escalating to a full POP outage at 11:38 UTC. Technical teams are already for troubleshooting.

    Preliminary findings:

    • No hardware or power failure detected at this stage.

    • Active investigation to pinpoint the root cause (optical link, third-party equipment, etc.).

    We will provide an update shortly with an ETR and further technical details. Your patience is appreciated.

    Next update: Within 30 minutes (or sooner if progress is made).

    Regards

Perte de lien FTTH liés à l’opérateur d’infrastructure Bouygues Telecom
  • Résolu
    Résolu

    Bonjour,

    Les services sont stables depuis hier midi.
    L’incident est désormais clos.

    Cordialement,

    Support Ielo



    Hello,

    Services have been stable since yesterday noon.
    The incident is now considered closed.

    Regards,

    Support Ielo

  • Surveillé
    Surveillé

    Bouygues Telecom vient de finaliser un rollback complet sur l’ensemble des serveurs impactés par cet incident. L’opérateur rapporte une amélioration significative du trafic et des services.

    Si vos services ne sont pas encore rétablis, nous vous invitons à :

    * Redémarrer vos routeurs .

    * Contacter le support technique ielo via l'extranet pour une analyse approfondie en cas de persistance des anomalies.

    Nous maintenons cet incident générique ouvert en surveillance active jusqu’à confirmation définitive de la résolution côté partenaire et infrastructure.

    Cordialement,

    Bouygues Telecom has completed a full rollback on all servers affected by this incident. The carrier reports significant improvement in traffic and service availability.

    If your services are still disrupted:

    * Reboot your routers .

    * Engage ielo technical support via extranet ticket for deeper troubleshooting if issues persist.

    We are keeping this generic incident ticket open under active monitoring until full resolution is confirmed on both partner and infrastructure sides.

    Regards,

  • Mettre à jour
    Mettre à jour

    Bonjour à tous,

    Nous revenons vers vous concernant l’incident FTTH en cours sur l’infrastructure Bouygues Telecom.

    Informations reçues de l’opérateur :

    -Impact : Perte de service nationale pour les clients Wholesale

    -Début d’impact : 28/10/2025 à 01h00 (heure locale)

    -Action en cours : Intervention sur les serveurs d’authentification RADIUS de Bouygues

    -Délai prévisionnel de rétablissement : 12h

    Nous poursuivons le suivi avec l’opérateur et vous tiendrons informés dès la reprise des services ou à l’expiration du délai communiqué.

    Cordialement,

    Support IELO

    ---

    Hello everyone,

    We are providing an update regarding the ongoing FTTH incident impacting Bouygues Telecom’s infrastructure.

    Information received from the operator:

    -Impact: Nationwide service loss for Wholesale customers

    -Impact start: Oct 28, 2025, at 00:00 UTC

    -Current action: Intervention on Bouygues’ RADIUS authentication servers

    -Estimated restoration time: 10:00 UTC

    We continue to closely monitor the situation with the operator and will provide an update as soon as services are restored or once the announced timeframe expires.

    Regards,

    Support IELO

  • Identifié
    Identifié

    Bonjour à tous,

    L’opérateur a identifié un incident majeur sur un équipement réseau , lié à une opération planifiée mal, provoquant des échecs d’authentification RADIUS (taux d’échec estimé entre 25 % et 50 %).

    Statut actuel :

    Aucun délai de résolution (ETA) n’a été communiqué par Bouygues Telecom à ce stade.

    L’incident impacte uniquement les services FTTH dépendants de leur infrastructure.

    Prochaine communication :

    Une mise à jour sera diffusée à 11h00 (heure française) ou dès réception d’informations critiques de l’opérateur.

    Nous suivons la situation en temps réel et restons à votre disposition pour toute question urgente.

    Cordialement,

    ---

    Dear Team,

    The operator has identified a major incident on a core network device, caused by a failed scheduled operation, resulting in RADIUS authentication failures (estimated failure rate: 25–50%).

    Current Status:

    No ETA (estimated time to resolution) has been provided by Bouygues Telecom at this stage.

    The incident exclusively impacts FTTH services dependent on their infrastructure.

    Next Update:

    A follow-up will be issued at 09:00 UTC (Oct 28, 2025) or sooner if critical updates are received from the operator.

    We are actively monitoring the situation in real time and remain available for urgent requesst.

    Best regards,

  • Détecté
    Détecté

    Bonjour à tous,

    Nous confirmons une interruption multiple des services FTTH sur le réseau de l’opérateur d’infrastructure Bouygues Telecom, détectée ce jour à 01h30 (heure locale).

    Actions en cours :

    Une demande d’analyse prioritaire a été transmise à Bouygues pour investigation.

    Nos équipes techniques poursuivent leurs vérifications en parallèle, notamment sur l’infrastructure IELO (liée à Bouygues), où aucun défaut n’a été identifié à ce stade.

    Prochaine communication :

    Une mise à jour détaillée sera partagée à 10h40 (heure locale) ou dès que des informations significatives seront disponibles.

    Nous restons mobilisés pour rétablir la situation dans les meilleurs délais. Merci de votre vigilance.

    Cordialement,

    Dear Team,

    We are currently investigating a multi-service FTTH outage on Bouygues’ infrastructure network, first detected at 00:20 UTC (Oct 28, 2025).

    Current Actions:

    A priority analysis request has been escalated to Bouygues Telecom for root-cause investigation.

    Our technical teams are actively monitoring the situation, including the IELO infrastructure (linked to Bouygues), where no faults have been detected so far.

    Next Update:

    A detailed status report will be provided at 08:40 UTC (Oct 28, 2025) or sooner if critical information arises.

    We are fully engaged in resolving this issue promptly. Thank you for your attention.

    Best regards,

Perte de connectivité access - Celestat (67)
  • Résolu
    Résolu

    L’incident a été identifié comme un défaut sur une carte d’uplink du routeur d’accès.
    La carte défectueuse a été remplacée et le service est désormais pleinement rétabli.
    Incident résolu à [heure locale actuelle : 22 octobre 2025, 19h15].

    ________________________________________________________________________

    The incident was caused by a fault on the uplink card of the access router.
    The faulty card has been replaced, and the service is now fully restored.
    Incident resolved at 17:45 UTC on October 22, 2025.

  • Mettre à jour
    Mettre à jour

    ETA terrain : 17h45 (heure locale, 22/10/2025). Nos équipes sont en route avec du matériel de rechange. Diagnostic et rétablissement seront engagés dès l’arrivée sur site.
    Impact : inchangé jusqu’à l’intervention.
    Nous publierons une nouvelle mise à jour à l’arrivée ou en cas d’évolution de l’ETA.


    Field team ETA: 2025-10-22 15:45 UTC. Engineers are en route with spares; diagnostics and recovery will start upon arrival.
    Impact: unchanged until intervention.
    Next update will be posted on arrival or if the ETA changes.

  • Détecté
    Détecté

    Nous observons un défaut sur la liaison d’un équipement d’accès dans le secteur de Sélestat (Bas-Rhin)depuis 14:34:22.
    Actions en cours : nos équipes techniques sont en déplacement avec du matériel de rechange pour diagnostic et rétablissement sur site.
    Impact : dégradation ou indisponibilité possible pour les services raccordés à ce nœud.
    ETA : non disponible pour le moment. Nous communiquerons un point d’avancement dès que nous aurons plus d’informations.


    We are investigating a fault affecting the uplink of an access device in the Sélestat area since 12:34:22UTC.
    Current actions: field engineers are en route with spare parts for on-site diagnosis and recovery.
    Impact: possible service degradation or outage for customers connected to this node.
    ETA: not available yet. We will provide an update as soon as more information is confirmed.

Perte d'un pop à Courbevoie
  • Résolu
    Résolu

    Les services sont stables depuis hier soir. À ce stade, nous n’avons pas encore reçu de retour de la part de l’hébergeur concernant l’incident du 20/10. L’incident était et reste escaladé côté IELO et auprès de l’hébergeur.
    Nous clôturons cet incident générique. Les retours de l’hébergeur seront ajoutés en commentaire sur cet incident dès réception. La supervision reste active et aucune anomalie n’est détectée.


    Services have remained stable since the evening of 20 Oct 2025. We have not yet received feedback from the hosting provider regarding the 20 Oct incident. The case has been and remains escalated both internally and with the hosting provider.
    We are closing this generic incident. Any provider feedback will be posted as a comment on this incident upon receipt. Monitoring remains active and no anomalies are currently observed.

  • Mettre à jour
    Mettre à jour

    Bonjour,

    Nous n’avons pas encore de retour de la part du gestionnaire du site.
    Une relance a été effectuée de notre côté.

    Nous reviendrons vers vous dès que nous aurons davantage d’informations.

    Cordialement,
    Support IELO



    Hello,

    We have not yet received any feedback from the site manager.
    A follow-up has been made on our side.

    We will get back to you as soon as we have more information.

    Regards,
    Support IELO

  • Surveillé
    Surveillé

    Bonjour,

    Nous détectons le POP de nouveau opérationnel depuis 15h36.
    En parallèle, une demande a été faite auprès du gestionnaire du site afin d’obtenir davantage d’informations.
    Nous maintenons nos équipements sous surveillance et poursuivons les investigations.

    Prochaine communication à 16h30 (heure locale).

    Cordialement,
    Support IELO


    Hello,

    We detected the POP back online at 13:36 UTC.
    In parallel, a request has been made to the site manager for further information.
    Our equipment remains under monitoring while investigations continue.

    Next update at 14:30 UTC.

    Regards,
    Support IELO

  • Identifié
    Identifié

  • Détecté
    Détecté

    Bonjour,

    Nous observons une perte de connectivité sur l’un de nos POPs à Courbevoie à 15h04.
    Des investigations sont en cours afin d’en déterminer l’origine.

    Une prochaine communication est prévue à 15h45 (heure locale).

    Cordialement,
    Support IELO



    Hello,

    We are observing a connectivity loss on one of our POPs in Courbevoie to 13:04 UTC.
    Investigations are in progress to determine the root cause.

    The next update is scheduled at 13:45 UTC.

    Regards,
    Support IELO

01/10 à 01/12

Suivant